Existing conditions

Which as-built drawings do you need for a commercial renovation?

Choose the sheets a renovation actually needs, mark what the team can verify on site, and check the delivered CAD files against independent measurements.

Plan A Services

November 24, 2026

November 25, 2026

Cutaway building above its measured floor plan.

Suppose you’re turning two retail bays into a clinic. A measured floor plan can tell you where a new reception desk fits. It won’t tell you whether a duct crosses the route above the desk, or how high the storefront sill sits. Before ordering a survey, give the architect three things: the decisions they need to make, the places those decisions depend on, and the surfaces they need measured. Here’s how to turn that conversation into a drawing order.

Choose the views your design team will use

Start with the work boundary on a marked-up plan. Include the connections just outside it: the corridor a new door opens into, the shaft a duct connects to, or the landing beyond a proposed threshold. A sheet that stops at the lease line can leave the most consequential dimension off the page.

Which view answers the renovation question?
Design decisionAsk forDetail to name in the brief
Move walls or combine suitesMeasured floor planFinished wall faces, openings, columns and overall dimensions tied across both spaces.
Replace lighting or ceilingsReflected ceiling plan (RCP)Ceiling types, changes in height, bulkheads and visible fixtures. Identify the reference floor for spot heights.
Route a duct beneath a beamSection cut along the proposed crossingFloor, underside of the beam and visible services at that specific crossing. Mark the cut on the plan.
Fit casework to an existing wallInterior elevation plus a plan detailOpening widths, sill and head heights, offsets and changes in wall finish. Identify which face was measured.
Change a storefront or entranceExterior elevation and threshold sectionAdjacent grades or landings within scope, opening location and level changes on each side.
Coordinate stacked floors or shaftsLinked floor plans and vertical sectionShared datum, floor-to-floor heights and visible edges of openings. Identify inaccessible floors.
Three schematic views of a corridor: a swinging door in plan, fixtures and an obstruction in ceiling plan, and the height of the obstruction in section.
The floor plan locates the opening. The reflected ceiling plan locates overhead features. A section through the crossing shows their heights. Schematic only.

New York City’s Department of Design and Construction takes a similar approach in its own consultant guide: document affected areas and select plans, elevations, sections and observable details as applicable. Its requirements belong to its projects. For a private renovation, use the list to start a conversation with the architect. NYC DDC Design Consultant Guide, section Z/06/B, Existing Conditions Drawings (PDF)

Find out what the old drawings actually represent

Ask who created the existing file, when, for what purpose, and whether later tenant work appears in it. An old permit plan may show a proposed partition. A contractor’s closeout markups may record a change at that partition. Neither tells you that its current face was measured last month. In a discussion among architects, contributors use “as-built” for different deliverables. Avoid that ambiguity by putting the survey date, visible conditions and areas of work in the order. Practitioner discussion about as-builts and field-measured existing conditions

Send the survey team the legacy files, but agree how they may use them. A practical drawing legend distinguishes field-observed geometry, information carried forward from a named record, and areas with no reliable information. Ask for a dated boundaries plan with locked rooms and inaccessible ceilings marked. Blank space on a drawing is too easy to read as empty space in the building.

Write a brief that two vendors can price the same way

A floor area alone leaves too much open. Mark the named rooms and floors on an exhibit, draw the two or three section lines that matter, and identify who can arrange access. Then name the person who will open and accept the files. The CAD manager may need a different deliverable from the property manager who reviews a PDF.

What to put in the request for proposal
Brief itemExample instruction
Extent and accessSuites A and B, connecting corridor up to grid 4, and the public side of the lobby entrance. Property manager to confirm access to the tenant storage room.
Drawing listOne dimensioned floor plan, one RCP of the revised ceiling area, one storefront elevation and two sections at the marked crossings.
Reference systemState drawing units, project north, level names and the elevation used as zero. Tie sections and spot heights to that datum.
Files and conventionsEditable DWG in the agreed version plus plotted PDF. Name layers, references, sheet sizes and the revision date.
Checks and exceptionsIdentify critical dimensions before capture, agree how they will be compared, and require an exception log and correction procedure.

A scope paragraph you can adapt

“Measure the accessible existing conditions in the areas shaded on Exhibit A. Deliver the sheets on the attached list as editable DWG and review PDF. Use finished faces for room dimensions and identify the elevation datum on each section. Label record-derived information and show inaccessible areas on the coverage plan. Before final issue, submit the agreed independent dimension checks and list unresolved discrepancies by room and sheet.”

Check the drawings before the design team builds on them

Select a few high-consequence dimensions before the survey: a clear opening, a corridor width and an offset near a tie-in. Define both endpoints and the measurement height. Comparing a frame opening on site with a clear passage dimension on paper can make a correct drawing look wrong. Where a check is close to the agreed limit, review the reference method and its uncertainty with the survey lead.

Worked example: drawing versus independent check
LocationDrawingIndependent checkAbsolute difference
Door opening912 mm910 mm2 mm
Corridor width1,804 mm1,801 mm3 mm
Column to wall2,475 mm2,486 mm11 mm
Absolute differences are 2, 3 and 11 millimeters. Only the column-to-wall distance exceeds the example 6 millimeter limit.
Invented values for a sample agreement with a 6 mm maximum difference per check. The three checks illustrate the method. They do not establish a whole-building accuracy level.

The third result deserves a marked-up location, confirmation of the endpoints, and a recheck or correction before the design uses that offset. An average across the three measurements would hide where the problem is. NIST’s guide for GSA explains how a formal acceptance plan uses a specified tolerance and independent observations. For contractual acceptance, agree on the sampling and decision rules in advance. NIST, Guidelines for Accepting 2D Building Plans (PDF)

See how a scan becomes a floor plan

In Leica’s AutoCAD walkthrough, watch how the technician chooses a slice through the scan before tracing geometry. That choice matters in a real building: a slice through a counter or a sill can produce a different outline from a slice through the open room. Ask your drafter which surface an important line represents.

Watch Leica’s 2D floor plan from a laser scan tutorial on YouTube

Open the final package like a new team member

  1. Open the DWG on a second workstation. Resolve missing external references, fonts or linked files, then confirm the units against a known dimension.
  2. Find each section cut on the plan and follow it to the section sheet. Check the cut passes through the actual crossing in question.
  3. Compare one room, one opening and one level label across the PDF and CAD file. Record the issue date alongside the check.
  4. Give the exception log to the designer. Decide who will resolve each location, by when, and which design choice must wait.

If the deliverable is a set of editable sheets, start with Plan A’s as-built plans. If consultants need to coordinate the building in three dimensions, use the scan-to-BIM scope checklist to specify the model alongside the sheets.